How to perform DR test step by step.
There are two components are Disaster recovery concept (SRM/vSphere replica). Mainly SRM tool help perform DR test/plan can perform.
Test plan: It is helpful to verify it works as expected.
> Login SRM tool and go to protection group which VM's needs to perform on it.
> Choose Protection group and select recovery plan which receptive group.
> Always perform test before perform Planned migration/Diester recovery.
> Test results will get show everything.
> To fix the issue if any issue identified during the test.
> We can proceed further planned migration/Disaster recovery option.
> If you choose Disaster recovery option before enable " true" option in advance settings.
> Once completed, recovery test process then reprotected the same VM's.
> Perform the validation checks on all vm's after completed DR test from source vCenter to target vCenter.
> You can see each step on during the rest/plan and troubleshoot the issue if facing any issue.
> If everything is good, re-apply same process back to target vCenter to source vCenter.